Consideration and issuance of projects in JSC "Astana-REC"
Projects for cable lines are reviewed on Mondays and Wednesdays from 9:00 am to 12:00 pm at the following addresses: Dомalak Ana Street 9, office 104 – for the right bank, and Syganak Street 56 – for the left bank.
You must bring the following documents in a sealed package:
- Technical conditions for the power supply of the facility;
- Two copies of the working project;
- A power of attorney for the right to approve projects from the client or design organisation.
Cable line projects are reviewed in the project approval department on Mondays from 10:00 am to 12:00 pm and on Thursdays from 2:00 pm to 4:00 pm.
Projects for transformer substations (TP), compact transformer substations (KTP), main distribution boards (VRU), overhead lines (OH lines), and connection to OH lines are reviewed on Tuesdays and Thursdays from 10:00 am to 12:30 pm at the address: Dомalak Ana Street 9, ground floor.
You must bring the following documents in a sealed package:
- Copies of technical conditions for connection to the electrical networks;
- Two copies of the project;
- A power of attorney for the right to approve projects from the client or design organisation.